| Groveton to Champion - Completed |
| Champion to Quicksilver - To be completed fall 2001 |
| Quicksilver Bridge - Completed |
| Quicksilver to McDonald - Completed |
| McDonald to Venice - Design and engineering underway,
preliminary work under way |
| Venice to Greer - Completed |
| Greer to Rt. 19 - Design and engineering underway |
| Rt. 19 to Library Jct. - Completed (Arrowhead Trail) |
| Library Jct. to Brownsville Rd - Design and
engineering underway |
| Brownsville Rd to Triphammer Rd - Completed |
| Triphammer Rd to Snowden - Design and engineering
underway |
| Snowden to Gill Hall - Completed |
| Gill Hall to Large - Construction scheduled to begin in
fall 2001 |
| Large to Clairton - Design and engineering
underway |
|
|
|
| West End Bridge to Station Square - |
| Station Square to 9th St. - |
| 9th St. to east side of UPMC Sports Center - Open
on a combination of completed and temporary
trail (Southside
Riverfront Park) |
| UPMC Sports Center to Sandcastle - Design and
engineering underway |
|
|
|
| Alongside Sandcastle - |
| Sandcastle to Lowes Theater - Acquisition of R/W
underway |
| Lowes Theater to Lowes Building Center - (1 mile of
trail ) Completed |
| Lowes Building Center to east edge of Waterfront - (1
mile of trail) Under construction 2001 |
| Waterfront to Kennywood Amusement Park -
Acquisition of R/W underway |
| Kennywood Amusement Park to McKeesport - Design and
engineering underway |
| McKeesport to Clairton - Signed for bike lanes and
shared roadway |
|
|
|
| McKeesport Marina to 15th St. Bridge - Completed |
| 15th St Bridge to McKeesport city limits on east side
of Youghiogheny - Completed |
| McKeesport city limits to Boston on east side of
Youghiogheny - use back streets near river (low traffic)
to Boston Bridge, then walk bikes on sidewalk across
bridge |
| 15th St. Bridge to Dead Man's Hollow on west side of
Youghiogheny- Pavement in place, no fencing. Active construction
- this section is closed.
Official opening at Youghtoberfest Oct 6-7 |
| Dead Man's Hollow to Connellsville - Completed
|
|
|
|
| Connellsville to Confluence - Completed |
|
|
|
| Confluence to Salisbury Viaduct - Completed |
| Salisbury Viaduct to Meyersdale - To be completed 2002 |
| Meyersdale to Big Savage tunnel - Engineering
underway |
| Big Savage Tunnel - Evaluating bids |
| Big Savage Tunnel to State Line - Investigating
construction options |
|
|
|
| State Line to Cumberland - Design and engineering
underway |